Cost-Plus Contract: Reimbursing Allowable Costs Plus a Negotiated Fee
Also called cost-plus contract, cost-plus contracting, cost-plus-fixed-fee contract, CPFF contract, cost-plus-award-fee contract, CPAF, cost-plus-incentive-fee contract, CPIF
A cost-reimbursement contract in which the buyer pays the seller's allowable incurred costs up to a ceiling plus a separately negotiated fee, which may be fixed (CPFF), formula-adjusted (CPIF) or judgmentally awarded (CPAF); used for work too uncertain to price in advance.
- Kind
- Practice
- Added
- 2026-11-19
- Markdown
- View on GitHub
A cost-plus contract is a cost-reimbursement arrangement in which the buyer pays the seller’s allowable incurred costs and adds a separately negotiated fee. Under the US Federal Acquisition Regulation (FAR), such contracts set an estimated total cost, used to obligate funds, and a ceiling that the contractor exceeds at its own risk unless the contracting officer approves more money.1 The defining feature is that the government, not the contractor, carries most of the risk that the work costs more than expected; the fee structure determines how much profit motive is left to control that cost.12
Variants and how they work
FAR subpart 16.3 recognises several fee designs.1 In a cost-plus-fixed-fee (CPFF) contract the fee is set at award and does not move with actual cost, which FAR itself describes as giving the contractor only minimal incentive to control cost. A CPFF contract can take a completion form, tied to a defined end product, or a term form, which buys a level of effort over a fixed period; FAR prefers the completion form when the work can be defined.1 In a cost-plus-incentive-fee (CPIF) contract the fee is adjusted by a formula comparing actual allowable costs to a target, while a cost-plus-award-fee (CPAF) contract pairs a base fee, possibly zero, with an award amount set by the government’s judgmental evaluation of performance.1 Cost-sharing and no-fee cost contracts sit at the edge of the family, for partners who expect offsetting benefits such as research results.1
Fees are capped. A CRS overview reports that a CPFF fee generally cannot exceed 10 percent of estimated cost, 6 percent for architect-engineering services and 15 percent for experimental, research or development work.2 The cost-plus-a-percentage-of-cost variant, where profit rises automatically with spending, is banned outright: CRS traces the bans to a 1949 civilian statute and a 1956 defense codification, and notes that contracts entered into by mistake in that form are void.2
When it may be used
Because the buyer underwrites cost risk, FAR restricts the type to work whose requirements or costs cannot be estimated well enough for a fixed price, such as research and early development.1 Use requires a written acquisition plan approved above the contracting officer, a contractor accounting system adequate to segregate contract costs, and enough government staff to oversee performance; the type is prohibited for commercial products and services.1 FAR also says CPFF normally should not continue into major-system development once risk reduction has shown the objectives to be achievable.1
Evidence and critiques
Economic theory explains both the appeal and the cost of the form. Bajari and Tadelis model a buyer who must pay to complete a design and trade stronger cost incentives against the transaction costs of renegotiating when plans change; they find cost-plus contracts are preferred as projects become more complex, offering microfoundations for transaction cost economics.5 The flip side is weak cost discipline: a National Research Council review of the Department of Energy found that decades of cost-plus-award-fee management and operating contracts delivered speed and flexibility in the Cold War, but fostered a culture in which neither the agency nor contractors were adequately accountable for cost and schedule.6
Award fees, meant to restore incentives, have often failed to. GAO’s December 2005 review of Defense Department award- and incentive-fee contracts (FY1999-2003) estimated about $8 billion in award fees paid regardless of outcomes, with a median of roughly 90 percent of available fee paid. CPAF was the most common type in its sample, and about 60 percent of those had a zero base fee.3 Programs with large cost growth, including the F/A-22 and the Joint Strike Fighter, still earned 91 and 100 percent of available award fee.3 GAO reports that DOD implemented six of its seven recommendations, but not the one to pay award fees only for above-satisfactory performance.4
Example
DOE’s nuclear complex grew out of the wartime Manhattan Engineer District, whose research and construction contracts became cost-reimbursed management and operating contracts; the model let Hanford and Savannah River facilities be built in under five years but was later blamed for weak financial control and cost growth.6
Connections
The cost-plus contract is a part of the menu of government contract types and contrasts with the fixed-price contract, which places cost risk on the seller.12 It is regulated by the Federal Acquisition Regulation and depends on rules for allowable cost, which define what can be reimbursed.1 Because the seller’s effort is hard to observe, it is a textbook setting for the principal-agent problem and tends to cause moral hazard, which incentive and award fees try to mitigate.35 Contract theory and transaction cost economics supply the rationale for when it beats fixed pricing.5 The contracting officer must justify and oversee it, cost data behind its estimates fall under the Truth in Negotiations Act, and DOE’s management and operating contracts are a prominent example.126
Sources
- FAR Subpart 16.3 - Cost-Reimbursement ContractsAcquisition.gov (FAR Council / GSA)
- Contract Types: An Overview of the Legal Requirements and Issues (R41168)Congressional Research Service (Kate M. Manuel), via EveryCRSReport
- Defense Acquisitions: DOD Has Paid Billions in Award and Incentive Fees Regardless of Acquisition Outcomes (GAO-06-66)U.S. Government Accountability Office, via GovInfo
- GAO-06-66 product page and recommendation statusU.S. Government Accountability Office
- Incentives versus Transaction Costs: A Theory of Procurement ContractsRAND Journal of Economics 32(3), 387-407 (Patrick Bajari and Steven Tadelis), via IDEAS/RePEc
- Improving Project Management in the Department of Energy, Chapter 4: Acquisition and ContractingNational Research Council, National Academies Press (1999)