Material Requirements Planning

Also called MRP, MRP I, materials requirements planning

A computerized production-planning method that converts a master production schedule into time-phased orders for components and raw materials by exploding bills of materials, netting out inventory and offsetting by lead times; the archetypal "push" system for dependent demand.

Kind
Practice
Added
2026-11-09

Material requirements planning (MRP) is a planning method for assembled products in which each stage of manufacturing tells its supplier, whether an upstream process or an outside vendor, which parts it needs and when.1 It was designed for dependent demand: once the quantity of finished goods is fixed, the quantity of every component follows by calculation, and cheap computing made those calculations practical at scale.1 The University of Cambridge’s Institute for Manufacturing describes MRP, together with its successor MRP II, as probably the most widely used planning and scheduling tool in the world.1

Origin

MRP systems spread in the 1970s, and Joseph Orlicky’s 1975 book Material Requirements Planning became the field’s reference text; Orlicky himself counted only 26 items, mostly articles and trade-press pieces, in the MRP literature at the time.3 IBM’s COPICS manuals of the same era documented the logic in far more detail than anything earlier.3 A 2016 historical study in the International Journal of Production Research argues that the core logic is older: production planning offices of the 1940s, descended from Frederick Taylor’s planning office, already exploded bills of materials using punched-card accounting machines, and limited data-handling capacity, not missing ideas, was the main barrier before the 1960s.3 Today’s enterprise resource planning (ERP) systems descend from those 1970s MRP systems.3

How it works

MRP separates independent demand (customer orders and forecasts, captured in the master production schedule) from dependent demand for components and raw materials.2 Its inputs are the master production schedule, an item master holding each part’s bill of materials, lot-sizing rule and planned lead time, and current inventory status.2 The calculation then runs level by level down the product structure:12

  • Explosion: the bill of materials converts end-item quantities into gross requirements for each component.12
  • Netting: on-hand and scheduled inventory is subtracted to give net requirements.12
  • Lot sizing: net requirements are grouped by a rule such as lot-for-lot, fixed order period or fixed order quantity, which may use an economic order quantity.2
  • Offsetting: orders are released one planned lead time before they are needed, and those planned releases become the gross requirements of the next level down.12

The outputs are planned order releases, change notices and exception reports.2 Uncertainty is handled with safety stock for quantity risk and safety lead time for timing risk.2

Evidence and critiques

MRP rests on three assumptions: capacity is sufficient (hence the label “infinite capacity scheduling”), lead times can be known in advance, and the due date is a valid anchor for back-scheduling.1 Each is a common failure point. Deterministic plans meet a random shop floor, schedules can prove infeasible, planners pad lead times to absorb variability, and “nervousness” sets in, where small deviations trigger large schedule changes, extra setups and confused workers.2 MRP II answered the capacity problem by wrapping MRP in demand management, rough-cut and detailed capacity planning, and shop-floor control within a planning hierarchy.2

The push-versus-pull debate is not one-sided. A 2004 simulation study of multi-product manufacturing found that where advance demand information was available, MRP-type push strategies achieved better inventory and service levels than kanban, which showed significant inefficiencies, and that safety lead time beat safety stock at low and medium loads.4 More recently, demand-driven MRP (DDMRP), which appeared in 2011, places strategic inventory buffers inside the MRP logic to bridge push and pull; a 2021 systematic review judged the approach promising but not yet mature, with parameter setting and robustness still needing research.5

In practice

A 2015 doctoral case study at a printing-ink manufacturer illustrates both the limits and the fixes. The firm’s ERP-based MRP planning produced late deliveries, stock that did not match demand and general instability, symptoms the author linked to known MRP limitations.6 Simulating DDMRP against the company’s historical ERP decisions cut high- and low-inventory alerts by about 45% and stock-outs by about 95% over the study period, though the author cautioned that a single case cannot attribute all the gain to DDMRP.6

Connections

MRP sits under production planning and control and inventory management, and it depends on two data structures, the bill of materials and the master production schedule.12 It was codified in Joseph Orlicky’s 1975 book Material Requirements Planning, has roots that a historical study traces to Taylor’s scientific management planning office, was followed by manufacturing resource planning (MRP II), and evolved into enterprise resource planning.23 It contrasts with kanban and just-in-time pull control, a contrast the simulation evidence shows depends on demand visibility.24 Its lot-sizing step can use the economic order quantity, and its capacity blind spot is what Theory of Constraints methods and demand-driven MRP, which it influenced, try to repair.256

Sources

  1. Materials Requirements Planning (MRP)Institute for Manufacturing, University of CambridgeAcademic, opened 2026-11-09
  2. Material Requirements Planning and Manufacturing Resources Planning (lecture notes, MIT 2.854)MIT OpenCourseWareAcademic, opened 2026-11-09
  3. The origin of materials requirements planning in Frederick W. Taylor's planning officeInternational Journal of Production Research (via CORE)Peer-reviewed, opened 2026-11-09
  4. Re-Examining the Performance of MRP and Kanban Material Control Strategies for Multi-Product Flexible Manufacturing SystemsInternational Journal of Flexible Manufacturing Systems (Springer)Peer-reviewed, opened 2026-11-09
  5. Demand Driven Material Requirements Planning (DDMRP): A systematic review and classificationJournal of Industrial Engineering and ManagementPeer-reviewed, opened 2026-11-09
  6. Interpreting and applying demand driven MRP: a case studyNottingham Trent University (DBA thesis)Academic, opened 2026-11-09