Executive and client communication

Escalating a problem

Also called escalation communication, escalating an issue, raising an escalation, joint escalation

Deliberately taking a problem, risk or disagreement that cannot be resolved at your level to the person with the authority to decide - early, with the facts, the options and a specific ask, and with the other parties informed rather than bypassed - so that escalation works as a normal decision route instead of a complaint or an act of blame.

Kind
Technique
Level
Intermediate
Evidence
Practitioner advice
Added
2026-11-11

Escalating a problem means taking an issue, risk or disagreement that cannot be settled at your level to someone with the authority to decide it. Done well, it is an ordinary governance route, not a complaint: project-management guidance treats it as a check on decisions that resolves problems early, cuts rework and makes priorities clear.1 Formal delivery standards build it in, giving each manager tolerances on cost, time, scope, quality and risk and requiring anything beyond those limits, or that the owner cannot resolve, to go to the next level.3

Origin

Escalation has no single inventor; it grew out of project governance. The UK government’s project delivery standard, for example, sets out tolerances, delegated authority and the expectation that unresolved risks and issues move up the work hierarchy to the senior responsible owner and sponsoring body.3 Practitioner writing in PMI’s PM Network turned the idea into personal guidance - when to escalate, who starts it and how to behave while it is pending.1 More recently, Hughes and Salvatore argued in MIT Sloan Management Review (2025) that organisations should formalise the procedure so disagreements are first worked on jointly by the people involved, instead of each side lobbying a sympathetic leader.5

Why it matters

The main failure is not escalating badly but not escalating at all. Information-systems research calls the reluctance to pass bad news upward the “mum effect”. Smith, Keil and Depledge (2001) built an explanatory model of it and tested it experimentally, finding that how serious staying silent seemed, and how much wrongdoing people observed, explained a significant share of reluctance to report.6 A 2008 laboratory experiment by Park, Im and Keil found that who was at fault affected willingness to report, and that time urgency raised it indirectly - suggesting managers can encourage early escalation by stressing how narrow the window to fix a problem is.2 Research on employee silence by Morrison, See and Pan (2014), across a lab study and two surveys, found that people who feel powerless at work are less likely to raise problems, an effect that weakens when the supervisor is seen as open to input.4

The opposite failure is the one-sided escalation. When colleagues take a disagreement separately to leaders likely to back them, a leader may endorse a poor decision on partial information, and trust between the parties suffers.5

How to apply it

Escalate when the trigger is clear: the issue exceeds your tolerance or delegated authority, or a genuine attempt to resolve it directly has stalled.13 Practitioner guidance suggests starting within about two working days of concluding it cannot be resolved at your level, telling your own manager first, and informing the other parties so the meeting stays factual.1 Where possible, escalate jointly: both sides document how they tried to resolve it and bring the disagreement together.5 Lead with the decision needed and the cost of delay, then the facts and options - the standard expects reports to highlight risks, issues and the decisions or direction required.3 Keep working the current plan until a decision is made.1

Agree the route before you need it. Governance frameworks should set out authority limits and who decides what, and leaders should document and teach the escalation process so people know it is legitimate to use; with clients, agree that path at kickoff so using it later does not read as an accusation.13

Common mistakes

Typical errors are waiting too long out of fear of conflict or looking bad, escalating before making a real effort to resolve the issue, making it personal, going over someone’s head without telling them or your manager, arriving without facts, and halting work while a decision is pending.1 Leaders make a matching mistake: if they meet escalations with irritation, they teach people to stay silent, since perceived openness is what weakens the link between powerlessness and silence.4

Evidence

The evidence is stronger on the problem than on the technique. The mum effect has experimental support in IT project settings, including tests of a whistle-blowing model adapted to project reporting.26 The silence research supports leader openness as a moderator.4 The specific practices here - joint escalation, a two-day rule, answer-first framing - are practitioner guidance that has not been tested in controlled studies, so the evidence status is practitioner.15

Connections

Escalation is part of managing up and draws on bottom line up front, since the decision and deadline must come first.3 It addresses the mum effect, the reluctance to report bad news studied by Park, Im and Keil and modelled by Smith, Keil and Depledge,26 and employee silence, which Morrison and colleagues link to felt powerlessness.4 It is applied in project status reporting, where reports should surface issues and decisions required.3 It sits next to selling issues to leadership (proposing opportunities upward) and delivering bad news, and depends on the psychological safety that makes raising problems feel safe.4 A RACI matrix helps by making clear in advance who decides.3

How to do it

  1. Check the trigger - the issue exceeds your authority or agreed tolerance on cost, time, scope or risk, or a disagreement has stalled after a genuine attempt to resolve it directly.
  2. Decide within a couple of working days and book time with the decision maker, rather than waiting for the next scheduled report.
  3. Tell your own manager, and tell the other party that you are escalating and why; invite them to escalate jointly with you.
  4. Write the escalation answer-first - the decision needed, by when, and the cost of delay - then the facts, the options with trade-offs, and your recommendation.
  5. Describe the problem, not the people; state each side's position in terms its owner would recognise.
  6. Keep working the current plan until a decision is made, then confirm the decision in writing to everyone affected.

Before and after

A product team lead's launch depends on a platform team that has just moved the shared release date by three weeks, and two conversations between the leads have not resolved it.

Before
Hi Priya (VP), I need to flag that the platform team has blown up our launch again. They won't commit to anything and we're going to miss the date because of them. Can you please sort this out?
After
Priya, Sam (platform) and I need a decision from you by Thursday: hold the 3 March launch with a reduced feature set, or move it to 24 March for the full release. Platform has to take three weeks for a security fix; we agree on the facts but not the priority. Options, costs and our two recommendations are in the attached one-pager. We are continuing to the current plan until you decide.

Why it works. The rewrite is a joint escalation with the other party copied and their position fairly stated, leads with the decision and deadline, offers options instead of blame, and confirms work continues - the moves practitioner guidance recommends - rather than asking a senior leader to take a side on a one-sided account.

Ask yourself

  • Have I genuinely tried to resolve this directly, and does it really exceed my authority or tolerance?
  • Does the other party know I am escalating, and would they agree my summary states their position fairly?
  • Could the decision maker act on my first two sentences alone - the decision, the deadline and the cost of waiting?

Sources

  1. Take it to the topProject Management Institute, PM Network 25(1) (Neal Whitten, 2011)Institutional source, opened 2026-11-11
  2. Overcoming the Mum Effect in IT Project Reporting: Impacts of Fault Responsibility and Time UrgencyJournal of the Association for Information Systems 9(7) (Park, Im and Keil, 2008)Peer-reviewed source, opened 2026-11-11
  3. Government Functional Standard GovS 002: Project delivery (version 2.0)UK Infrastructure and Projects Authority (2021)Government source, opened 2026-11-11
  4. Why Employees Often Don't Speak UpNYU Stern School of Business, Faculty Research (Morrison, See and Pan, 2014)Academic source, opened 2026-11-11
  5. Formalize Escalation Procedures to Improve Decision-MakingMIT Sloan Management Review (Jonathan Hughes and Gabriella Salvatore, 2025)Practitioner-journal source, opened 2026-11-11
  6. Keeping Mum as the Project Goes Under: Toward an Explanatory ModelJournal of Management Information Systems 18(2) (Smith, Keil and Depledge, 2001)Peer-reviewed source, opened 2026-11-11